Project Information
- Client: Hurlstone Park Station Stairs
- Location: Hurlstone Park NSW 2193
- Service: Full Demolition of existing Staircase
Constructa Group successfully completed the full demolition of an existing staircase structure at Hurlstone Park Station, servicing two platforms. This complex project required precise planning and execution to ensure safety and minimal disruption to the surrounding rail infrastructure.
The scope of works included:
Complete demolition of the staircase structure across both platforms
Deployment of a 500-tonne crane to safely rig and remove stair components
Oxy cutting of steel elements for controlled dismantling
Use of specialised demolition equipment and machinery
Installation of propping and scaffolding to ensure structural stability and worker safety throughout the operation
Despite the technical challenges, our team executed the project efficiently and in full compliance with rail safety and local regulations.
This project highlights Constructa Group’s expertise in handling intricate and high-risk demolition works in operational transport environments.